Street Improvement Project Schedule - Nov. 1-5

PITTSFIELD, Mass. (Oct. 29, 2021) – Please note the following work is scheduled for Nov. 1-5, as
part of the City of Pittsfield’s 2021 Street Improvement Project.
The schedule is as follows:

Monday, Nov. 1: Raising structures on Yarmouth Street and Anita Drive; berm on Lucille Street and
Paul Avenue; also on Paul, patch pipe crossing.

Tuesday, Nov. 2: Raising structures on Yarmouth Street and Anita Drive; pave Cliff and Curtain
avenues, and Maloney Street.

Wednesday, Nov. 3: Raising structures on Yarmouth Street and Anita Drive; pave Lucille and Hawk
streets, and Paul Avenue.

Thursday, Nov. 4: Pave Yarmouth Street and Anita Drive (weather permitting).

Friday, Nov. 5: Rain date to accommodate scheduled work potentially impacted by Thursday’s
expected inclement weather.

On-street parking is prohibited during this work between the hours of 6 a.m. and 6 p.m. each day.

The schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for
your patience during this time.