Street Improvement Project Schedule - Aug. 16-20

Please note the following work is scheduled for Aug. 16-20, as part of the City of Pittsfield’s 2021 Street Improvement Project.

The schedule is as follows:

Monday, Aug. 16: structure adjustments on Dalton Avenue; minor clean up on Dexter and Dillon streets and Cadwell Road.
Tuesday, Aug. 17: structure adjustments continue on Dalton; lowering and plating structures on Plumb Street.
Wednesday, Aug. 18: shim on Cadwell, Hawthorne Avenue, Brenton Terrace, Oxford and Buel streets; structure work continues on Plumb.
Thursday, Aug. 19 – Friday, Aug. 20: pave top on Dalton; structure continues through end of Thursday on Plumb; shim Huron, Dexter, and Dillon streets, if time permits.

On-street parking is prohibited during this work between the hours of 6 a.m.-6 p.m. each day, with the exception of Monday’s clean-up work on Dexter, Dillon, and Cadwell.

Please note the schedule is subject to change based on weather conditions.