Street Improvement Project Schedule Update - Sept. 10-13

Please be advised of the following work that will take place Sept. 10-13, as part of the City of Pittsfield’s 2019 Street Improvement Project.

During this work, on-street parking will be prohibited in all locations mentioned below.

Tuesday, Sept. 10: Finish pave on Maple Grove Drive.

Wednesday, Sept. 11: Finish pave on Doreen Street.

Thursday, Sept. 12: Finish pave on Birch Grove Drive and Parkside Avenue.

Friday, Sept.13: Finish pave on Julianna, Andrea, and Filomena drives.

Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.