Street Improvement Project Schedule Update - Aug. 23-30

Please be advised of the following work that will take place Aug. 23-30, as part of the City of Pittsfield’s 2019 Street Improvement Project.

During this work, on-street parking will be prohibited in all locations mentioned below.

The schedule is as follows:

Friday, Aug. 23:  Loam, seed and cleanup on Essex, Plymouth, and Franklin streets.

Monday, Aug. 26: Loam, seed and cleanup on McKinley Terrace, Boylston Street, Bay State Road, and Parkside Avenue.

Tuesday, Aug. 27: Finish pave on Essex, Plymouth, and Franklin streets and McKinley Terrace.

Wednesday, Aug. 28 and Thursday, Aug. 29: Raising structures on Doreen Street and Juliana, Filomena, and Maple Grove drives.

Friday, Aug. 30: Finish pave on Onota Street and Bay State Road.

Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.