Street Improvement Project Schedule Update - week of Sept. 24

 

PITTSFIELD, Mass. – Please be advised of the following work that will take place during the week of Sept. 24, as part of the City of Pittsfield’s 2018 Street Improvement Project.

The schedule is as follows:

Monday, Sept. 24: finish pave on Crofut and McKay streets.

Tuesday, Sept. 25: finish pave on Maplewood Avenue.

Wednesday, Sept. 26: final pave on Hubbard Avenue. Removal and installation of aprons begin on Columbus Avenue.

Thursday, Sept. 27 – Friday, Sept. 28: removal and installation of aprons continue on Columbus and Hubbard avenues.

 During this work, there will be a single lane closure and limited access on Crofut. Additionally, there will be no parking and a single lane closure on McKay Street and Maplewood Avenue.

 Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.